In order to ensure a long lasting beautiful patio, driveway, or wall installation, Page Landscaping follows these steps each and every time.
After deciding the location of the project. We set out boundary markers and then excavate 12″ beyond on all sides. This will give us a stabile foundation to build our project on. It also gives us a solid base to install our paver edge restraint.
The sub-base is graded out and then compacted using a minimum of 7,000 psi compactor. Compaction is the most important aspect of a quality paver installation
This is a layer of geo-textile fabric installed between the sub-base and the new base material. It’s purpose is to keep the new base material from migrating into the sub-base. Although ICPI does not require it. We install it on most of our projects.
The base thickness will depend on the project being installed. Walkways and patios will require a minimum of 6″ of gravel base. A residential driveway will have 12″ or more of base. The base material is 3/4″ minus gravel. It is installed in lifts of 3-4″ and compacted between each lift multiple times to achieve full compaction. The base is a critical part of the finished project. We make sure that the base is pitched properly to achieve the desired slope and runoff needed. We install the base to a variance of +/- 3/8″ over a 10′ span.
Page landscaping uses only concrete sand as recomended by ICPI. We will never use Stone dust or screenings under our paver projects as they hold moisture and can cause failure of the finished project. We use 1″ guide rails to assure that a uniform layer of bedding sand is installed.
We install a wide variety of pavers from all different manufactures. The pavers and laying pattern are selected by the homeowner. The pavers are laid onto the freshly screeded bedding sand. pavers are cut to fit with a diamond bladed wet saw or a hand held diamond cut off saw.
We install plastic brick edge along all exposed outside edges. The edging is held in place by 10″ spikes placed a maximum of 8″ apart. We use pave tech flexible and rigid edging as we feel this is the best edging on the market today.
The pavers are now compacted into the bedding sand with a compactor rated for 4,000-5,000 psi. If there are any broken pavers they are replaced at this time.
We use polymeric joint stabilizing sand for between the pavers. The polymeric sand helps to reduce the amount of weeds and ants that come up between the pavers.
The pavers are again compacted to vibrate the polymeric sand between the pavers. The entire area is given a final sweeping and then wet down lightly to set up the polymeric sand
We cleanup all areas of your yard that have been disturbed by our work. This includes adding loam and seed along the edges of the new pavers or adding new mulch along a patio to blend in with the existing mulch. The driveway and staging areas are broom swept also. We feel that the homeowner should be able to enjoy the project as soon as we leave the property.